At what design capacity percentage must trapped sediment be removed while maintaining temporary erosion and sedimentation controls?

Prepare for the NICET Highway Construction Inspector Level III Exam with interactive questions and detailed explanations. Master construction standards and techniques to boost your career!

The correct design capacity percentage at which trapped sediment must be removed while maintaining temporary erosion and sedimentation controls is 50 percent. This guideline is critical in managing sediment accumulation and ensuring the effectiveness of erosion and sediment control practices during construction activities.

When temporary measures, such as silt fences or sediment basins, become filled to 50 percent of their capacity, they may begin to lose their effectiveness in trapping additional sediment. Allowing the sediment to accumulate beyond this level can lead to increased erosion, compromised water quality, and potential violations of environmental regulations. Therefore, proactive maintenance and sediment removal at the 50 percent threshold is crucial to ensure that these control measures perform as intended and minimize the impact of sediment runoff.

The importance of adhering to this percentage lies in maintaining both environmental protection and compliance with best management practices. Such actions contribute to sustainable construction processes and responsible land management.