What must the contractor do before it rains during the installation of drainage?

Prepare for the NICET Highway Construction Inspector Level III Exam with interactive questions and detailed explanations. Master construction standards and techniques to boost your career!

Before rain impacts the construction site, it is crucial for the contractor to aim to complete the entire drainage system. This is because a functional drainage system plays a vital role in managing water runoff and preventing water accumulation, which can impede work and lead to more significant issues such as erosion, flooding, or damage to already installed components.

Completing the installation of the drainage system prior to rainfall ensures that proper water management is in place. This minimizes the risk of water affecting the construction work, preserves the integrity of materials and the installation process, and helps maintain site safety. A completed drainage system can effectively channel rainwater away, thus reducing the likelihood of delays or complications that could arise from adverse weather conditions.

While check valves might be necessary, it is not their installation that ensures immediate protection against rain; and simply replacing damaged pipes or pausing all work do not proactively address the main objective, which is to have a functioning drainage system before rainfall occurs. Prioritizing the completion of the entire system is the most effective strategy to mitigate the risks posed by rainy weather during the installation process.

Subscribe

Get the latest from Examzify

You can unsubscribe at any time. Read our privacy policy